2009 airport award information/bid results
Bid tabulations are held confidential and are not published until an award has been made. If all bids are rejected, no bid tabulation will be published. In addition, individual bids that were determined to be irregular, unit prices for those rejected bids will also not be provided.
The following documents are presented in Adobe PDF format.
| The following project in this table will utilize American Recovery and Reconstruction Act of 2009 funds (ARRA). | ||||
| Airport name | Project | Award date | Award amount | Contractor |
| Burlington Municipal | ARRA/AIP-04 | May 5, 2009 | $1,137,908.00 | B.R. Amon & Sons Inc. |
| Austin Straubel International | ARRA-38 | May 14, 2009 | $1,961,046.40 | Triple P. Inc. (Peters Concrete Co.) |
| Dane County Regional | ARRA-43 | May 18, 2009 | $3,267,489.56 | Trierweiler Construction and Supply Co., Inc. |
| Dodge County | ARRA-09 | May 21, 2009 | $305,666.58 | Pieper Electric, Inc. |
| Wittman Regional | ARRA-30 | May 21, 2009 | $1,968,981.76 | LaLonde Contractors |
| Rhinelander Oneida County | ARRA-28/AIP-29 | May 27, 2009 | $2,061,436.56 | Pitlick & Wick, Inc. |
| Airport name | Project | Award date | Award amount | Contractor |
| Dane County Regional | AIP-41 contract 3 | January 15, 2009 | $3,161,817.71 | Speedway Sand and Gravel |
| Outagamie County Regional | AIP-34 | January 26, 2009 | $611,577.30 | RMD Holdings Ltd. |
| La Crosse Municipal | February 26, 2009 | $138,015.64 | De Bauche Truck and Diesel | |
| Amery Municipal | AIP-02 | March 20. 2009 | $252,668.50 | Dresel Construction Co. LTD |
| Lancaster Municipal | AIP-03 | March 20, 2009 | $230,385.00 | Westmore Industries |
| Marshfield Municipal | AIP-07 | March 25, 2009 | $730,461.20 | Trierweiler Construction and Supply Co. |
| 2009 State Sealcoat Program | March 25, 2009 | $286,595.96 | Fahrner Asphalt Sealers, Inc. | |
| 2009 Federal Sealcoat Program | April 27, 2009 | $234,867.40 | Fahrner Asphalt Sealers, Inc. | |
| Merrill Municipal Airport | AIP-04 | April 29, 2009 | $348,936.06 | A-1 Excavating Inc. |
| Outagamie County Regional | AIP-36 | April 29, 2009 | $1,584,728.00 | Elmstar Electric |
| Hartford Municipal | AIP-05/SAP-53 | April 30, 2009 | $196,992.99 | Ford construction Co., Inc. |
| Richland | AIP-05 | April 30, 2009 | $416,020.00 | VJS Lincoln Inc. |
| Sawyer County | AIP-03 contract 3 | April 30, 2009 | $77,643.00 | Century Fence Company |
| Sheboygan County Memorial | AIP-20 contract 2 | April 30, 2009 | $154,150.00 | Highway Landscapers |
| Menomonie Municipal | AIP-11 | May 26, 2009 | $574,310.00 | Shefchek Builders |
| La Crosse Municipal | SAP-66 | May 27, 2009 | $307,661.55 | Mathy Construction Company |
| Dane County Regional | AIP-44/SAP 80 | May 29, 2009 | $5,786,722.75 | Trierweiler Construction and Supply Co, Inc. |
| Chippewa Valley Regional | SAP-57 | June 2, 2009 | $1,466,843.90 | McCabe Construction, Inc. |
| Sheboygan County Memorial | AIP-21 | June 3, 2009 | $969,947.25 | James Peterson Sons |
| Burnett County | AIP-03/SAP-54 | June 5, 2009 | $1,063,987.60 | Dresel Construction, LTD |
| Washington Island | AIP-06 | June 5, 2009 | $516,883.60 | TBJ Corporation of Wisconsin |
| Madeline Island | AIP-06 | June 16, 2009 | $1,350,345.18 | Antczak Construction Inc. |
| Outagamie County Regional | AIP-37 | June 18, 2009 | $932,475.00 | Miron Construction Co., Inc. |
| 2009 Statewide runway marking program | SAP-30 | June 19, 2009 | $54,899.00 | Fahrner Asphalt Sealers, LLC |
| Chippewa Valley Regional | AIP-30 | June 22, 2009 | $1,648,893.22 | Chippewa Concrete Services, Inc. |
| Crandon Municipal | AIP-05 | June 22, 2009 | $112,092.58 | American Fence Company |
| Manitowish Waters | AIP-06 | June 22, 2009 | $568,012.55 | Cedar Falls Building Systems, Inc. |
| Dane County Regional | SAP-76 | July 2, 2009 | $1,098,014.10 | Hoffman Construction Co. |
| Dane County Regional | SAP-78 | July 2, 2009 | $428,221.90 | Struck & Irwin |
| Dane County Regional | SAP-79 | July 2, 2009 | $583,584.90 | Payne & Dolan Inc. |
| La Crosse Municipal | AIP-33 contract 1 | July 24, 2009 | $4,223,418.35 | Integrity Grading & Excavating Inc. |
| La Crosse Municipal | AIP-33 contract 2 | July 24, 2009 | $713,930.00 | Strupp Trucking |
| La Crosse Municipal | AIP-33 contract 3 | July 24, 2009 | $314,191.70 | A-1 Excavating Inc. |
| La Crosse Municipal | SAP-67 | July 24, 2009 | $526,739.00 | Fowler & Hammer Inc. |
| West Bend Municipal | AIP-13 | July 29, 2009 | $567,171.00 | Payne & Dolan, Inc. |
| Austin Straubel International | AIP-39/SAP-72 | August 4, 2009 | $7,991,115.83 | Miron Construction Co., Inc. |
| Cumberland Municipal | AIP-06 | August 11, 2009 | $133,791.11 | Dresel Construction Co. |
| Southern Wisconsin Regional | AIP-28 | September 15, 2009 | $628,284.74 | Rock Roads Companies |
| JD Bake Memorial | AIP-09 | October 26, 2009 | $162,772.00 | METCO |
Questions about the content of this
page:
Thomas DeWinter, thomas.dewinter@dot.wi.gov
Last modified: August 14, 2012
All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.