Northeast Region weekly construction update
May 16, 2013
The Wisconsin Department of Transportation (WisDOT) NE Region in Green Bay is providing a weekly update on region construction, which includes the counties of Brown, Calumet, Door, Fond du Lac, Kewaunee, Manitowoc, Marinette, Oconto, Outagamie, Sheboygan, and Winnebago.
Construction-related traffic impact exists in the locations listed below. Closures listed are subject to change and are weather-dependent.
Regionwide
NE Region backbone routes – Beam guard end treatment upgrades
Schedule: April 22 to June 28, 2013
Length: n/a
Cost: $1.2 million
Location: Various highways throughout NE Region
Description: Guardrail removal and installation, grading operations, and traffic
control. There are a total of 56 sites within Brown, Outagamie, Winnebago, Fond du Lac, Calumet and
Manitowoc counties requiring upgrades to beam guard and end treatments. Lane closures will be
changing weekly as sites are completed.
Brown County
For information on the US 41 major project, please check the project website.
WIS 160, Village of Pulaski
Schedule: May 13 to October 15, 2013
Length of project: 0.63 miles
Cost: $1.4 million
Location: WIS 160 from Brown County/Shawano County line to St Augustine St.
Description of work: This project involves the reconstruction of WIS 160 from
Highview Street to St. Augustine Street in the village of Pulaski. This project includes storm
sewer placement, curb and gutter, sidewalk, colored aprons, asphalt pavement.
May 13 to May 17: The contractor worked on removing pavement and starting
storm sewer.
May 20 to May 24: The contractor will continue to place storm sewer.
Traffic impacts: The road will be closed from St. Augustine Street to Highview
Street. The detoured route is WIS 32 to WIS 29.
US 41 Orange Lane to Glory Road, Main Avenue (County G) Interchange
Schedule: March 2012 through June 2013
Length: Mainline 3.5 miles (Orange Lane – Glory Road); Main Avenue (County G) –
0.5 miles (Spirit Way – Lawrence Drive)
Cost: $57 million
Location: Town of Lawrence, city of De Pere, village of Ashwaubenon; Brown County
Description of project: This project will reconstruct US 41 Mainline between
Orange Lane and Glory Road and the reconstruction of the Main Avenue interchange and replacement of
bridges over Ashwaubenon Creek, Main Avenue, and Grant Street.
May 13 to May 17: Sign structure and drainage pipe work continued. Placement of
breaker run, base material, trimming and mainline concrete pavement continued on the outside lanes
of northbound and southbound lanes of US 41. Structure work consisted of placing bridge aprons
adjacent to the US 41 bridges over County EE and County G.
May 20 to May 24: Sign structure work will continue as well placement of
asphaltic base on northbound lanes south of County EE and on the Scheuring Road northbound on-ramp.
Concrete pavement will be placed in the northbound lanes south of County EE.
Traffic impacts: US 41 northbound and southbound shoulders closed from March
5, 2012 to June 21, 2013 from 1.5 miles south of Scheuring Road to Parkview Road. US 41
northbound and southbound lanes are restricted to 11 feet from 1.5 miles south of Scheuring Road to
Parkview Road with speeds reduced from 65 mph to 55 mph within the project limits and north through
the WIS 29 Interchange project. Shoulders will also be closed on the Scheuring Road
interchange ramps as well as the Ashland Avenue and Main Avenue southbound on-ramps. The Scheuring
Road westbound turn lane to US 41 northbound will be closed through June 5. Alternate access
is available within the roundabout. On Monday, May 20 beginning at 12:01 a.m., the northbound
off-ramp and southbound off-ramp from Scheuring will be closed until 3 a.m. The northbound
off-ramp from Scheuring Road will also be closed on May 21 from 9 a.m. to 2 p.m. On May 21 through
May 23, the left lane of the County G northbound off- ramp will be closed. On May 23 to May
24, the right shoulder of the County G southbound on-ramp will be closed. On May 30, the right
shoulder of the County G northbound on-ramp will be closed.
County VK, Ashwaubenon, Brown County
Schedule: April 22 to June 28, 2013
Length of project: 0.11 miles
Description of work: The project work includes grading, common excavation,
base aggregate, concrete pavement, concrete curb and gutter, storm sewer, permanent signing,
pavement marking, traffic signals and all incidental items necessary to complete the as shown on
the plans and included in the proposal and contract.
May 13 to May 17: Vinton Grading crews continued with removals and crush base
aggregate on site. Vinton placed breaker run and base course. Martell and Vinton began to prepare
for paving towards the end of the week, setting string line grades. Electricians were installing
conduit on the south side of Lombardi.
May 20 to May 24: Electricians will be installing traffic signal loops. Vinton
will begin concrete pavement and continue paving throughout the week.
Traffic impacts: Argonne closed to all traffic. County VK (Lombardi Avenue),
various lane closures – two lanes of traffic will remain open in both eastbound and westbound.
US 41/ WIS 29 Interchange Core Project – US 41 major
Schedule: August 2012 to October 2014
Length: 1.6 miles along US 41, 0.8 miles along WIS 29
Cost: $97 million
Location: US 41 (Mason Street to Memorial Drive)/WIS 29 (County J to Taylor
Street)
Description: This project will complete the reconstruction of the US 41 and WIS 29
interchange, converting the interchange by building high speed, free flow flyover ramps, along with
adding capacity to US 41. Included in this project is the construction of 12 bridges, 15 retaining
walls, 30 sign bridges, concrete pavement, asphalt pavement, storm sewer, stormwater detention
ponds and landscaping, while incorporating many community sensitive design features.
May 13 to May 17: New US 41 bridge construction continued at Shawano Avenue, crews
continued decking operations. Crews set concrete girders at Packerland Drive for the new WIS 29
bridges, and sign bridge construction also continued throughout the project. Structural steel
girders continued to be set west of US 41 for the future flyover bridge structures. Crews also
continued the removal of a portion of a box culvert north of Shawano Avenue on the west side of US
41. Retaining wall construction has resumed at Packerland Drive, Memorial Drive, and Shawano
Avenue. Grading operations began along northbound US 41 in the Shawano Avenue interchange area, as
well as continue on the new WIS 29 lanes east of Packerland Drive.
May 20 to May 24: New US 41 bridge construction will continue at Shawano Avenue,
crews will continue decking operations next week. At Memorial Drive, crews plan to perform a deck
pour at the northbound US 41 bridge next week. Crews will continue decking operations at Packerland
Drive for new WIS 29 bridges, and sign bridge construction will also continue. Structural steel
girders will continue to be set west of US 41 for the future flyover bridge structures, including
over the southbound off-ramp to US 41. Grading operations will continue along northbound and
southbound US 41 in the Shawano Avenue interchange area, as well as continue on the new WIS 29
lanes east of Packerland Drive. Asphalt base along with concrete pavement will begin along the
future southbound US 41 lanes between Mason Street and Shawano Avenue.
Traffic impacts: Each night between May 20 and May 23, there will be a northbound
US 41 lane closure from 8 p.m. to 5 a.m. between Mason Street and Memorial Drive. On May 22 and May
23, Packerland Drive will have lane closures from 6 p.m. to 6 a.m. between the WIS 29 ramps.
US 41 Beaver Dam Box Culvert Project - US 41 major
Schedule: April 2013 to May 2014
Length: 0
Cost: $6.9 million
Location: US 41 (Shawano Avenue to Velp Avenue)
Description: This project will complete the construction of the new Beaver Dam box
culvert between Shawano Avenue and Velp Avenue on US 41, a new storm water pond in the northwest
quadrant of US 41 and Velp Avenue, and reconstruct the cul-de-sacs of Island Court and Lone Grove
Avenue.
April 29 to May 3: Crews continued to grade the median of US 41. Crews began work
on the Beaver Dam Creek box culvert.
May 6 to May 10: Crews will begin grading on the west side of US 41. Crews will
continue to work on the Beaver Dam Creek box culvert.
Traffic impacts: There will be intermittent southbound lane closures between 7
p.m. and 5 a.m. and northbound lane closures between 8 p.m. and 7 a.m. on US 41.
US 41 Lakeview Drive
Schedule: August 2012 to May of 2013
Length: 0.1 miles
Cost: $3,324,000
Location: Lakeview Drive, Green Bay WI, Brown County
Description: Building retaining walls and reconstruction the Lakeview Drive
Bridge.
May 13 to May 17: Crews continued on the bridge walls, pave the surface of
Lakeview Drive, and began staining the bridge.
May 20 to May 24: Crews will continue staining the bridge and doing final
cleanup.
Traffic impacts: There will be intermittent shoulder closures on Lakeview Drive.
There will be one lane flagging operations on Lakeview Drive through the week of May 13. There will
be intermittent southbound lane closures between 7 p.m. and 5 a.m. and northbound lane closures
between 8 p.m. and 7 a.m. on US 41.
Leo Frigo Bridge, city of Green Bay/I-43
Schedule: May 2012 to July 2013
Length: 3.5 miles
Cost: $16.8 million
Location: I-43 over the Fox River
Description: Work consists of completing concrete deck surface repair and
placing an asphalt or concrete overlay on I-43 over the Fox River, Atkinson Drive over I-43, and
Military Avenue over I-43; replacing the bridge joints along I-43 over the Fox River and Military
Avenue over I- 43; painting of the steel girders within ten feet of the joint replacements, the box
girders along the arch span, and all steel within the splash zone along I-43 over the Fox River;
concrete pavement repairs along I-43 between Webster Avenue and Military Avenue and along with the
ramps at Webster Avenue and Atkinson Drive; traffic cameras at I-43/Danz Avenue, I- 43/University
Avenue, and I-43/County JJ; dynamic message signs at I-43/Glenmore Road, I- 43/Danz Avenue,
I-43/Military Avenue, and I-43/WIS 54/57; ramp gates at the Webster Avenue and Atkinson Drive
on-ramps to I-43; temporary and permanent storm sewer; beam guard replacement; median concrete
barrier wall; sign replacement; and pavement markings.
May 13 to May 17: Contractor finished placing the asphalt overlay along the I-43
southbound outside lane and shoulder across Leo Frigo Bridge; they started deck repairs along the
I-43 southbound inside lane and shoulder across Leo Frigo Bridge; they removed the median
crossovers along Atkinson Drive; and they began placing the concrete curb and gutter along the
Atkinson Drive median.
May 20 to May 24: Contractor will finish deck repairs along the I-43 southbound
inside lane and shoulders across Leo Frigo Bridge; they will finish placing the concrete curb and
gutter and place the concrete sidewalk along the Atkinson Drive median; and place the pavement
markings along Atkinson Drive.
Traffic impacts: Southbound I-43 is reduced to one lane from US 41 to Webster
Avenue and the posted speed limit has been reduced to 55 mph. The on-ramp from Atkinson Drive to
southbound I-43 is closed until late July. Atkinson Drive is down to one lane in each
direction. There are currently no lane or speed restrictions along northbound I-43.
Upcoming closures: I-43 northbound will be reduced to one lane from University
Avenue to Atkinson Drive starting the week of May 28. This closure is expected to remain in effect
until mid-July. I-43 northbound on-ramp from Webster Avenue will be closed starting the week of May
28. This closure is expected to remain in effect until mid-July. Military Avenue over I-43
will be closed starting the week of June 3. This closure will be in effect for 30 calendar
days.
WIS 29/County U and WIS 29/County VV
Schedule: April to June
Length: 1 mile
Cost: $1 million
Location: At the intersections of WIS 29/County VV and WIS 29/County U in Brown
County.
Description: Construction of J-turns at the WIS 29/County VV intersection and
intersection improvements at WIS 29/County U.
May 13 to May 17: Open J-turns east and west of WIS 29/County VV intersection to
traffic. Construction will begin at WIS 29/County VV median and WIS 29/ Marley Street/ Milltown
Road intersection.
May 20 to May 24: Continue construction WIS 29/ County VV intersection median and
WIS 29/Marley Street/Milltown Road intersection. Construction activities include storm sewer, curb
and gutter, and possibly asphalt.
Traffic impacts: The median crossover at WIS 29/County VV will be closed to
traffic. The traveling public will have to use the newly constructed J-turns when maneuvering
across WIS 29. A temporary intersection will be utilized while the WIS 29/Marley Street/ Milltown
Road intersection is under construction and closed to traffic.
For more information, visit the project page.
Brown/Outagamie County
WIS 54
Schedule: Late April to late June 2013
Length: 1.0 miles
Cost: $8.74 million
Location: WIS 54 from Oneida to Green Bay, County U to WIS 172
Description: This project involves the realignment of WIS 54 with a new bridge
over Duck Creek and construction of a roundabout at the intersection of WIS 54 and Seminary Road.
Work includes storm sewer, asphalt pavement, construction of a retaining wall, bridge
rehabilitation, lighting, signing, landscaping and pavement marking.
May 13 to May 17: Crews began rehab work on the old truss structure over Duck
Creek early this week.
May 20 to May 24: Rehab work will continue on the old truss structure over
Duck Creek throughout the week.
Traffic impacts: Traffic along WIS 54 will remain open at all times. Some
shoulder closures may be necessary to complete work but travel lanes along WIS 54 will remain open
during the 2013 construction season.
Calumet County
No state construction projects currently in progress.
Door County
Bayview Bridge
Location: WIS 32/57, Sturgeon Bay, Door County
Schedule: March 4 to July 4
Length of project: 0.3 miles
Description of work: The project includes structural steel repair, bridge
painting, electrical and machinery system upgrades, an overlay of the bridge deck and approaches.
This work is being done to extend the life of the bridge.
May 13 to May 18: Blasting, cleaning and painting operations to continue on
the south bascule leaf. Approach slab removals to start. Continuing to install conduit. Structural
steel repairs will continue on the north bascule leaf. Cleaning of the concrete parapets to start.
May 20 to May 24: Blasting, cleaning and painting operations to continue on
the south bascule leaf and flanking span. Continuing to install conduit and electrical wire.
Structural steel repairs will continue on the north bascule leaf. Cleaning of the concrete parapets
to continue. Form and pour the approach slabs.
Traffic impacts: Bridge closed to vehicular traffic and pedestrians. Detour
through city of Sturgeon Bay. For more project information, go to the
bridge rehab project
page.
Note: Bridge is closed to snowmobiles.
Fond du Lac County
No state construction projects currently in progress.
Kewaunee County
No state construction projects currently in progress.
Manitowoc County
No state construction projects currently in progress.
Marinette County
No state construction projects currently in progress.
Oconto County
No state construction projects currently in progress.
Outagamie County
No state construction projects currently in progress.
Sheboygan County
WIS 57
Schedule: April to October 2013
Length: 24 miles
Cost: $5.0 million
Location: Sheboygan County to Ozaukee/Sheboygan County line to
Manitowoc/Sheboygan County line
May 13 to May 17: New median curb and gutter was constructed at the
intersection between County A and Clearview Road. Construction of new traffic signals continued at
the intersection of WIS 57 and County PP, WIS 57 and Kiley Way, and WIS 57 and the westbound ramps
of WIS 23. Asphalt pavement was removed and concrete pavement placed at several location
throughout the project.
May 20 to May 24: Asphalt milling will begin between County O and WIS 32.
Construction of new traffic signals will continue at the intersection of WIS 57 and County PP, WIS
57 and Kiley Way, and WIS 57 and the westbound ramps of WIS 23.
Traffic impacts: WIS 57 will remain open to through traffic. Between County K
and County O, single lane closures will occur in areas of work. Between County O and WIS 32, work
will be completed using flagging operations.
I-43 Bridge Painting
Schedule: May 6 to June 24, 2013
Length of project: 0.0 miles
Cost: $710,000
Location: WIS 32 and County KK bridges over I-43
Description: The WIS 32 and County KK bridges over I-43 will have the structural
steel repainted. I-43 will remain open to traffic with single lane closures in both directions. WIS
32 will remain open to two-way traffic during bridge painting operations. County KK will be closed
to traffic during bridge painting operations. During closure, County KK will not be detoured.
May 13 to 17: The crew, after completing their painting work, will remove a
containment of the structural steel of the WIS 32 bridge from the west abutment to the middle of
the southbound I-43 highway. After the containment is down they will begin to work on the area from
the center of the southbound lane to the middle of the median. They will also continue to work from
the east abutment to the middle of the northbound I-43 highway. In this section the crew will
continue to remove the old paint and replace it with a new three-coat paint system. Afterwards the
containment will be removed and the lane they were working over will be opened up to traffic.
May 20 to 24: The crew will work on building a containment of the structural steel
of the WIS 32 bridge from the median to the middle of the southbound I-43 highway. They will also
continue to work from the east abutment to the middle of the northbound I-43 highway. Afterward the
containment will be removed and the lanes they were working over will be opened up to traffic.
Traffic impacts: The left, inside lane of southbound and the right, outside lane
of northbound I- 43 will be closed down underneath the WIS 32 bridge. A reduction of the posted
regulatory speed limit from 65 mph to 55 mph will be in place during the lane closure. The WIS 32
bridge over I-43 will remain open to two-way traffic. These closures on I-43 will be opened by noon
on Friday, May 24.
Winnebago County
For information on the US 41 major project, please check the project website.
WIS 26 – Breezewood Lane
Schedule: April to October 2013
Length: .66 miles
Cost: $924,721.75
Location: WIS 26 to WIS 21 (WIS 44 median work)
Description: Work consists of replacing the approach slabs, joints, and southeast
wing of the WIS 44 bridge over US 41, replacements of pavement, curb and gutter, concrete median
slope noses, and sidewalk, paving brick and landscaping curb, trees and perennials, and pavement
markings.
May 13 to May 17: The contractor completed work on the westbound portion of the
bridge over US 41 by pouring bridge approaches and pavement repairs. The bridge deck was being
cleaned and protected with a surface treatment and prepared for traffic.
May 20 to May 24: The contractor will switch traffic from the eastbound side on to
the westbound side. Traffic will be two directional on the westbound side of the bridge. The
contractor will begin removals on the east side of the bridge.
Traffic impacts: WIS 44 northbound and southbound lanes limited to one lane
in each direction with crossovers at the ramp terminal intersections. Northbound and southbound
traffic are counter-directional on the WIS 44 bridge across US 41. One traffic lane will be
maintained at all times for ramps.
US 41 reconstruction over Lake Butte des Morts – US 41 major
Schedule: August 2011 to July 2013
Length: 2 miles
Cost: $54.2 million
Location: WIS 21 Interchange, US 41 mainline from 1500 feet north of Witzel
Avenue, to the US 45 Interchange.
Description: This project involves the reconstruction of the WIS 21 interchange to
pass over US 41. The interchange will be completely reconstructed to include roundabouts at ramp
terminals and at the WIS 21 intersections with Washburn and Koeller Streets. This project also
includes the reconstruction of mainline US 41 from Witzel Avenue to the US 45 Interchange including
new bridges over Lake Butte des Morts and Sawyer Creek. The work on the Lake Butte des Mort
Causeway will include a recreational trail along the east side of US 41 crossing over the water.
May 13 to May 17: Crews continued concrete paving on the northbound lanes of US 41
over the Lake Butte des Morts causeway. Crews continued installing parapets on the main
channel bridge for northbound US 41. Crews continued staining concrete retaining walls and bridges
throughout the project.
May 20 to May 24: Crews will continue concrete paving on the northbound lanes of
US 41 over the Lake Butte des Morts causeway, installing parapets on the main channel bridge and
staining concrete retaining walls and bridges throughout the project.
Traffic impacts: The northbound and southbound shoulders of US 41 are closed
between US 45 and Witzel Avenue. Northbound and southbound US 41 are reduced to two, 11-foot lanes
in each direction between US 45 and Witzel Avenue.
US 41 Lake Butte des Morts Causeway landscaping and trail enhancements
Schedule: May to October 2013
Length: 1.5 miles
Cost: $1.45 million
Location: US 41 causeway from WIS 21 to US 45 Interchange.
Description: The work on the Lake Butte des Mort Causeway will include plantings,
kiosks, informational plaques, concrete sidewalk, walls, railings, and solar powered lighting.
May 13 to May 17: Crews began work on building the overlook railing foundations.
May 20 to May 24: Crews will continue work on the overlook railing
foundations. Work is also to begin on the railings above the fishing paths.
Traffic impacts: N/A
US 41 – Mainline (US 45 to Breezewood Lane)
Schedule: March 2011 to June 2013
Length: 8.0 miles
Cost: $45 million
Location: US 41 to US 45 Interchange to Breezewood Lane
Description: The project is entering the final stage of construction. Crews will
be working to install permanent concrete barrier wall, rumble strips, permanent pavement markings
and other minor items of work. All work is expected to be complete by June.
May 20 to May 24: Crews will be working on a culvert repair on the outside of US
41 northbound on Old Dixie Road this week. Crews will be on site constructing asphalt pavement pads
for the state patrol and county law enforcement at various locations on the outside shoulder of
northbound and southbound US 41 this week.
Traffic impacts: There will be shoulder closures in conjunction with the work this
week. All travel lanes will remain open.
Motorists are advised to use caution and remain alert when driving through any work zone and should:
- Buckle up for safety.
- Know where construction zones are located and allow extra time to get through them.
- Avoid the peak travel hours.
- Watch for special messages on electronic message boards as you approach major construction zones.
- Slow down, get into the correct lane early, and merge cautiously.
- Stay alert for surprise slow-downs.
- Take a scenic alternate route.
For more information regarding traffic impacts in the Northeast Region:
- Follow us on Twitter for regional alerts from the Traffic Incident Alert System and for construction related traffic advisories.
- Call 5-1-1 or visit Wisconsin 511 online.
Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information, contact:
Communications Manager Kim A. Rudat, WisDOT NE Region
(920) 492-5743,
kim.rudat@dot.wi.gov
Communications Manager Mark Kantola, WisDOT US 41 Project
(920) 492-4153,
mark.kantola@dot.wi.gov
| |

