WIS 25 Highways for Life project, Wabasha-Nelson weekly construction update
November 6, 2009
Work completed since last update:
- Continued deck removal at Bridge 2.
- Placed steel diaphragms to existing girders.
- Installed drain at north and south abutments of Bridge 2.
- Hauled and placed base aggregate for temporary bypass of Bridge 1.
- Removed existing riprap and topsoil at Bridge 3 temporary bypass.
- Continued to haul and place borrow at Bridge 1 temporary bypass.
- Began placing stabilization fabric for temporary bypass of Bridge 3.
Anticipated work schedule for the week of Nov. 9, 2009:
- Installing shear studs and tying iron at Bridge 2.
- Place stabilization fabric at Bridge 3 for temporary bypass.
- Hauling borrow and special backfill 2 stone for temporary bypass of Bridge 3.
- Decking on Bridge 2.
- Finishing slopes, placing riprap and topsoil on temporary bypass of Bridge 1.
Reminder: Weekly meetings with the contractor occur every Monday at 8 a.m. at the Field Office behind the Nelson City Building.
For more information, contact:
Chris Ouellette, WisDOT NW Regional Communications Manager
(715) 833-9814, (715) 828-9471,
Chris.Ouellette@dot.wi.gov
Wendy Maves, WisDOT Project Manager
(715) 836-3902,
Wendy.Maves@dot.wi.gov
| |