Work on I-39 in Marquette County scheduled to begin next week

March 21, 2014

Motorists can expect to encounter single lane closures and speed reductions

Bridge maintenance along I-39 in Marquette County is currently scheduled to begin Monday, March 24.

Zenith Tech Inc., of Waukesha is the prime contractor for the $1.3 million project. Improvements include:

  • Overlaying the I-39 northbound bridge over Neenah Creek with concrete.
  • Raising Grouse Drive over I-39 to meet current design and safety standards and painting the steel girders to extend the life of the bridge.
  • Overlaying the I-39 northbound bridge over County O with concrete.
  • Overlaying the I-39 northbound bridge over WIS 23/County P with concrete and applying an anti-skid treatment to the bridge surface.
  • Overlaying the I-39 northbound bridge over County CX with concrete and reinforcing the bridge slopes.

During construction, motorists on I-39 can expect to encounter single lane closures and a speed reduction to 55 mph. Grouse Drive will be closed after Memorial Day until mid-July. No formal detour will be posted.

Construction is scheduled for completion by mid-July 2014.

For more information, contact:
Kristin McHugh, WisDOT NC Region Communications