US 12 Environmental Impact Statement (EIS) schedule
Date Type of work/activity
September 2002 Notice of intent to prepare draft EIS (DEIS).
October 2002 First public information meeting (PIM).
September 2002 to February 2003 Agency and public scoping period.
February 2003 to July 2003 Develop purpose and need statement.
April 2003 Second PIM.
July 2003 to November 2003 Analysis of broad range of alternatives.
November 2004 Third PIM.
November 2003 to November 2005 Conduct studies and prepare DEIS on alternatives held for further study.
November 2005 Public hearing.
January 2006 to December 2006 Additional studies and agency coordination post-DEIS.
December 2006 to April 2007 Preferred alternative selection process and response to comments.
April 2007 to August 2008 Additional studies, public and agency coordination on preferred alternative, PIM number 4.
April 2007 to September 2008 Prepare final EIS (FEIS).
December 2007 Announcement of preferred concept.
2008-2009 Further detailed study of south bypass and preparation of FEIS.
Mid-2009 Publish FEIS.
Late 2009 Publish record of decision (ROD).
Late 2010  Officially map future bypass corridor.
 
top  Return to top


 

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index