US 14 reconstruction schedule

August to September 2005 - Resurfaced existing US 14 corridor from WIS 138 to WIS 92.

2010 - Reconstruct/expand US 14 to four lanes from County MM to WIS 138.

2010 - Resurface US 14 from US 12/18 to County MM.

2011 - Reconstruct WIS 138 from Park Street to Hill Road.

2016 - Construct new US 14 corridor from WIS 138 to WIS 92.