WIS 57 expansion project - schedule

Work on the WIS 57 expansion project began in summer 2004 and is scheduled for completion in 2008. Schedules differ by section.

Date Type of work/activity
Brown County P to north Kewaunee County line
Fall 2004 - Fall 2005 WIS 57 was prepared for expansion from Brown County P to the north Kewaunee County line.
Fall 2006 This section will be paved and opened to traffic.
2009 Existing WIS 57 will be resurfaced and transferred to local municipalities.
Door County H to WIS 42
Fall 2004 - Fall 2006 WIS 57 will be graded and paved from Door County H to WIS 42.
Fall 2006 This section will be open to traffic.
South Door County line to Door County H
2007 - 2008 WIS 57 will be graded, paved and opened as four lanes from the south Door County line to County H. Work on this 10-mile section will take place.


Traffic traveling on WIS 57.

Traffic traveling on WIS 57.

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index