I-39 Coloma - Fast facts
Coloma-Plainfield, Waushara County

Wisconsin 511 travel information
View NC, I-39 Coloma-Plainfield, in Waushara County in a larger map.
Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project limit.

Location

I-39, WIS 21 (Coloma) to WIS 73 (Plainfield), in Waushara County.

Overview 

WisDOT is doing bridge maintenance work on three structures located along I-39 in Waushara County:

  • Northbound I-39 over County CH
  • Southbound I-39 over County CH
  • And the WIS 21 bridge over I-39 in Coloma

The bridges are exhibiting signs of deterioration. The deterioration is due to a combination of age, surface wear, and weathering. In addition, the WIS 21 bridge over the northbound lanes of I-39 lacks desirable vertical clearance to accommodate oversize loads.

Promote your business during construction

Come In We're Open sign

Is your business located within mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

  • Environmental documentation - Complete
  • Preliminary design - Complete
  • Local officials meeting - Jan. 9, 2014
  • PIM - Jan. 23, 2014
  • Final design - Complete
  • Construction currently scheduled - Fall 2014 through fall 2015

Traffic impacts/Detours

The projects are scheduled to occur during two consecutive construction seasons:

2014

  • Stage 1: I-39 northbound shoulder preparation
    • Construction timeline: September - October 2014
    • Traffic impacts:
      • I-39 northbound: Single, weekday lane closures. No weekend lane closures.
      • WIS 21: No traffic impacts
      • County CH: No traffic impacts
  • Stage 2: I-39 northbound over County CH (bridge rehabilitation)
    • Construction timeline: October - November 2014
    • Traffic impacts:
      • I-39 northbound: Single lane closure with barrier wall and a 14 foot maximum width restriction during the first three weeks of construction.
      • WIS 21: No traffic impacts
      • County CH: No traffic impacts

2015

  • Stage 3: WIS 21 over I-39 (bridge raising and rehabilitation)
    • Construction timeline: March - May 2015 (before Memorial Day)
    • Traffic impacts:
      • I-39: Single, weekday lane closures in the northbound and southbound lanes
      • WIS 21: Bridge closed between ramp terminals; WIS 21 detoured via I-39
      • County CH: No traffic impacts
  • Stage 4: I-39 northbound overlay under WIS 21 bridge, I-39 southbound shoulder preparation and I-39 polymer overlays
    • Construction timeline: June - July 2015
    • Traffic impacts:
      • I-39: Single, weekday lane closures. No weekend lane closures.
      • WIS 21: No traffic impacts
      • County CH: No traffic impacts
  • Stage 5: County CH bridge painting
    • Construction timeline: July - August 2015
    • Traffic impacts:
      • I-39: Some shoulder closures near County CH
      • WIS 21: No traffic impacts
      • County CH: Single lane of traffic under bridges with barrier wall and temporary traffic signals
  • Stage 6: WIS 21 bridge painting
    • Construction timeline: September - November 2015
    • Traffic impacts:
      • I-39 staging (three stages):
      • Southbound outside lane closure with barrier wall
      • Northbound and southbound inside lane closures with barrier wall
      • Northbound outside lane closure with barrier wall
      • WIS 21: No traffic impacts
      • County CH: No traffic impacts

Status

Construction is currently scheduled to begin fall 2014.

Contact information

Kristin McHugh, WisDOT North Central Region Communications Manager
(715) 421-8380
kristin.mchugh@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
North Central Region, Wisconsin Rapids Office
1681 Second Ave. South
Wisconsin Rapids, WI 54495-4768
Phone: (715) 421-8301
Fax: (715) 423-0334
TTY: 711
Email: ncr.dtsd@dot.wi.gov

SSI - Project contacts Questions about the content of this page:
WisDOT North Central Region Office, ncr.dtsd@dot.wi.gov
Last modified: June 13, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.