I-39 Stevens Point Area Corridor Study - Schedule

Stevens Point exit 39/51/10.

For more information on Public Involvement Meetings (PIM), hearings and other public activities, visit Public involvement.

The proposed improvements, which are scheduled to take place between 2014 and 2024, represent an approximate $100 million construction investment in Central Wisconsin.

Current (this year)

  • 2014
    • The Environmental Report (ER) for the County B area is expected to be completed
    • The ER for the WIS 66 east/Stanley Street area is expected to be completed

Future (next year and beyond)

  • Summer 2015 - Environmental Assessment (EA) for the entire corridor is expected to be completed

Past (anything prior to today)

  • 2013 - Study concept development
    • Environmental Assessment (EA) continues for the entire corridor
    • Environmental Reports continue for the County B area and for the WIS 66 east/Stanley Street area.
    • No construction activity at this time
  • 2012 - Ongoing study and alternative development and evaluation
  • May 2011 - PIM
  • 2010 - Data collection/evaluation of existing conditions

SSI - Project contacts Questions about the content of this page:
WisDOT North Central Region Office, ncr.dtsd@dot.wi.gov

Last modified: June 17, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.