US 8 (Hay River - US 53) Corridor Preservation
Tier II, Poskin/Barron segment - Schedule

For more information on Public Involvement Meetings (PIM), hearings and other public activities, visit Public involvement.

Current (this year)

  • Nothing at this time

Future (next year and beyond)

  • 2015 - Tier II scheduled to be completed
  • To be determined (TBD) - Tier III is the final design and construction. In order to advance to this tier, the legislature needs to approve funding


Past (anything prior to today)

2012

  • Fall 2012 - Study completed

2011

  • July 27, 2011 - PIM

2010

  • 2010 - Study started

SSI - Project contacts Questions about the content of this page, contact:
WisDOT Northwest Region Office, nwr.dtsd@dot.wi.gov
Last modified: July 18, 2013

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.