WIS 93 Revitalization - Fast facts
Independence, Trempealeau County

Wisconsin 511 travel information
View NW, WIS 93 Revitalization - Independence, Trempealeau County in a larger map.
Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project limit.

The roadway is now open.

Location

WIS 93, A St. to Indee Blvd., in Independence, in Trempealeau County.

Overview

We are currently reconstructing WIS 93 in Independence. Additional improvements will include:

  • Reconstructing the WIS 93/WIS 121 intersection (including the addition of turn/auxiliary lanes)
  • Upgrading the existing storm sewer and street lighting
  • Replacing outdated sanitary and water utilities
  • Replacing Elk Creek Bridge

Promote your business during construction

Come In We're Open sign

Is your business located within mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

  • Miscellaneous work will be completed in spring 2015.

Traffic impacts/Detours

  • The roadway is open.

Construction update

Due to below normal temperatures, minor miscellaneous work will be completed in the spring of 2015. The work will not affect the traveling public. Essential parts of the project will continue to be completed this construction season.

Work to be completed this year:

  • Seeding
  • Sidewalk on the north side of County Q North
  • Asphalt side road connections and entrances
  • Concrete island at the intersection of WIS 121 and WIS 93
  • Topsoil work (to the extent possible)
  • Restoration (to the extent possible)

Work to be completed in spring 2015:

  • Topsoil
  • Seeding work
  • Driveway work
  • Other minor miscellaneous work

Status/phase

Project scheduled to be completed November 26, 2014.

Contact information

Dave Koepp, WisDOT Project Manager
(715) 836-2078
david.koepp@dot.wi.gov

Chris Ouellette, WisDOT Northwest Region Communications Manager
(715) 833-9814
chris.ouellette@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire WI
Phone (715) 836-2891 or toll-free (800) 991-5285
Fax: (715) 392-7863
Email: nwr.dtsd@dot.wi.gov

SSI - Project contacts Questions about the content of this page:
WisDOT Northwest Region Office, nwr.dtsd@dot.wi.gov
Last modified: November 20, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.