WIS 100/Mayfair Rd. Milwaukee - Fast facts
Milwaukee, Milwaukee County

Wisconsin 511 travel information
View SE, WIS 100/Mayfair Rd. in Milwaukee, Milwaukee County in a larger map.
Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project limit.

Location

WIS 100/Mayfair Rd., Burleigh St. to Silver Spring Dr. (118th Ct. to Mayfair Rd.), in Milwaukee, Milwaukee County.

Overview

On Mayfair Road

  • The roadway will be resurfaced
  • Traffic signals will be upgraded
  • Minor geometric improvements will be done at the intersections
  • Some medians will be updated to add left-turn lanes
  • Pedestrian curb ramps will be updated

On Silver Spring Drive

  • The pavement will be replaced
  • A sidewalk will be added to the north side of the road

The current condition of the roadway pavement is highly deteriorated. The traffic signal upgrades and pedestrian improvements will create a safer location for pedestrians to cross the street. The additional signal heads at each approach to the intersection will improve driver visibility. The addition of left-turn lanes in the medians will help create a safer condition for vehicles turning left.

Promote your business during construction

Come In We're Open sign

Is your business located within mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

March 2014 until late fall 2014.

Traffic impacts/Detours

  • During construction on WIS 100, from Burleigh to Hampton Ave., two lanes of traffic will be open in each direction during construction with turn lanes provided at signalized intersections.
  • From Hampton Ave. to Silver Spring Drive, one lane of traffic will be open in each direction with turn lanes provided at signalized intersections.
  • When night time operations are necessary, one lane of traffic will be open in each direction for the entire length of the project and turn lanes may be closed.

Status/phase

Construction

Contact information

Tom Lazcano, P.E., WisDOT Project Manager
(262) 574-5437
tom.lazcano@dot.wi.gov

Brian DeNeve, WisDOT Southeast Region Communications Specialist
(262) 548-8759
brian.deneve@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southeast Region
141 NW Barstow St.
P.O. Box 798
Waukesha, WI 53187-0798
Phone: (262) 548-5902
Fax: (262) 548-5662
TDD: 711
ser.dtsd@dot.wi.gov

SSI - Project contacts Questions about the content of this page:
WisDOT Southeast Region Office, ser.dtsd@dot.wi.gov
Last modified: March 12, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.