US 14 Reconstruction - Schedule

Existing US 14.

For more information on Public Information Meetings (PIM), hearings and other public activities, visit Public involvement.

Current (this year)

2014-2017 - Design work continues

  • US 14, WIS 138 to WIS 92 (Segment E)
  • Park and Ride lot (Segment F)

Future (next year and beyond)

2018-2024

  • US 14, WIS 138 to WIS 92 (Segment E) construction anticipated
    • Phases of the project shall be constructed over the next three to six years
  • Park and Ride lot (Segment F) construction anticipated


Past (anything prior to today)

2013 - Design work started

  • US 14, WIS 138 to WIS 92 (Segment E)
  • Park and Ride lot (Segment F)

2012 - Reconstruction of the US 14 and County MM interchange and County MM and County M
intersection completed (Segment D)

2011

  • Reconstruction of US 14 and WIS 138 interchange completed (Segment B)
  • City of Fitchburg project reconstruction phase of the placement of existing Lacy Road Overpass and McCoy Road interchange completed (Segment G)
  • Resurface US 14 from US 12/18 to County MM completed (Segment C)
  • PIMís
    • May 12, 2011 - PIM for US 14 and County MM interchange and County MM and County M
      intersection
    • Jan. 25, 2011 - PIM for WIS 138 and US 14 interchange
    • Jan. 25, 2011 - PIM to inform the community of the anticipated US 14 and WIS 138 interchange
      project construction duration, staging and traffic re-routing.

2010 - City of Fitchburg resurfaced the 4-lane segment on McCoy Road in the interchange area
(Segment G)

2009 - Reconstructed and expanded US 14 to four lanes from County MM to WIS 138 (Segment A)

Aug. 14, 2008 - Public hearing for the US 14 corridor projects (Segments A, B, C and E)

2006 - PIM for the US corridor projects (Segments A, B, C and E)

2005 - Resurfacing existing US 14 from West Rutland road to WIS 138 (Segment H)

Questions about the content of this page:
WisDOT Southwest Region Office-Madison, swr.dtsd@dot.wi.gov
Last modified: May 28, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.