US 10 expansion project - schedule

The proposed construction schedule began in 2006 with completion currently scheduled for 2012.

Current construction

Project: I-39/US 10 west interchange
Dates: August 2007 through August 2009
Description: A new interchange will be constructed north of the Portage County X overpass to provide high speed free-flow traffic access from I-39 to the new US 10 west bypass.
Traffic impacts:

  • I-39 traffic may be reduced to one lane in each direction.
  • The existing County X interchange was permanently closed in July 2008.
  • County X will remain as an overpass over I-39 after the project is completed.
  • Local access is available at the newly constructed Casmir Road interchange.
  • Crews will complete concrete paving operations in 2009.
  • Upon completion of the project in July 2009, US 10 traffic will use the newly constructed roadway from River Road to I-39.

Project: US 10, Long Road to River Road
Dates: September 2007 to August 2009
Description: Construction of a new four-lane freeway from Long Road to River Road. The project also includes a Portage County E overpass and a new interchange with WIS 34 north. 
Traffic impacts:

  • WIS 34 north and County E will remain open during the majority of the construction.
  • Crews will complete concrete paving operations in 2009.
  • Upon completion of the project in 2009, US 10 traffic will use the newly constructed roadway from WIS 34 north to River Road.

Project: US 10, Wood County N to Long Road
Dates: August 2009 through fall 2011
Description: Construction of a new four-lane freeway from Wood County N to Long Road. The project also includes overpasses at Portage County G and Portage County O and a new interchange with WIS 34 south.
Traffic impacts:

  • County G will remain open during the majority of construction except for short periods during off-peak travel times for certain construction activities.
  • County O will be closed for construction of an overpass for a period of three to four months.
  • Local road crossings of new US 10 at Long Road, Mallek Road, Clover Road, and Trestik Road will be closed.
  • There will be minor disruptions in the local road system adjacent to the project while local road modifications are constructed.
  • After construction of new US 10 is completed, it will be opened to traffic from Trestik Road to WIS 34 north.
  • After new US 10 opens to traffic in spring 2011, the intersection of existing US 10 and WIS 34 south will be closed, and crews will construct a new WIS 34 railroad overpass and WIS 34 south interchange. This closure will require WIS 34 to be detoured for four to six months via Wood County P and Wood/Portage County O.


 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index